Our Flagship Project
Wouterspan (Thornley) Diamond Mine
Northern Cape, ZA
The Thornley mine project stands as the Group's flagship endeavor for a valued client. Distinguished as the sole mine globally operating its processing plant on a dry basis, without reliance on water, it epitomizes innovation and sustainability in the mining industry.
Plant Configuration
High Tonnage Bourevestnic X-Ray Sorter Configuration
Timeline
Operations began in 2018 and have since expanded.
Key Metrics
Since 2018 up to now, production has risen from 25,000 tons per month to over 60,000 tons per month, at an average grade of 0,2 ct/100 tonne
Impact & Benefits
- We've discovered that heavy-banded ironstone deposits can be efficiently processed using high-tonnage X-ray sorters (such as Bourevestnik), replacing historically unsuccessful methods like pan plants or dense medium separation plants. In water-scarce regions like the Northern Cape, where water deposits are distant, we've developed water-free methods to process diamondiferous deposits. Eros is the first to successfully achieve this milestone.


Thank you for considering Eros Mining & Engineering.
We look forward to hearing from you and exploring how we can collaborate to achieve mutual success. Please don't hesitate to reach out to us with any inquiries or opportunities. We're here to serve you with excellence